5.3.8 Frio County Water Supply Plan
Table 5.3.8-1 lists each water user group in Frio County and their corresponding surplus or shortage in years 2030 and 2050. For each water user group with a projected shortage, or need, a water supply plan has been developed and is presented in the following subsections.
Table 5.3.8-1.
Frio County Surplus/Shortage
|
Water
User Group |
Surplus/Shortage1 |
Comment |
|
|
2030 |
2050 |
||
|
City of Dilley |
1,836 |
1,780 |
Projected surplus |
|
City of Pearsall |
1,225 |
1,108 |
Projected surplus |
|
Rural Area Residential and Commercial |
38 |
0 |
Projected surplus |
|
Industrial |
0 |
0 |
No projected demand |
|
Steam-Electric Power |
0 |
0 |
No projected surplus/shortage |
|
Mining |
0 |
0 |
No projected surplus/shortage |
|
Irrigation |
-76,506 |
-70,662 |
Projected shortage – see plan below |
|
Livestock |
0 |
0 |
No projected surplus/shortage |
|
1 From Table 4-8,
Section 4.1 – Water Needs Projections by Water User Group. |
|||
5.3.8.1 City of Dilley
The City of Dilley is projected to have adequate water supplies available from the Carrizo Aquifer to meet the city’s projected demand during the planning period.
Working within the planning criteria established by the SCTRWPG and the TWDB, it is recommended that the City of Dilley implement the following water supply plan (Table 5.3.8-2).
§ Municipal demand reduction (conservation) to be implemented in 2000. This project can provide an additional 51 acft/yr beginning in year 2000, decreasing to 34 acft/yr of supply in 2050 (See Section 6, Supplement 2 and Volume III, Section 1.1).
Table 5.3.8-2.
Recommended Water Supply Plan for the City of Dilley
|
|
2000
(acft/yr) |
2010
(acft/yr) |
2020
(acft/yr) |
2030 |
2040
|
2050 |
|
Projected Need (Shortage) |
0 |
0 |
0 |
0 |
0 |
0 |
|
Recommended Plan |
|
|
|
|
|
|
|
Demand Reduction (Conservation) (L-10 Mun) |
51 |
54 |
57 |
32 |
33 |
34 |
|
Total New Supply |
51 |
54 |
57 |
32 |
33 |
34 |
The costs of the recommended plan for the City of Dilley are shown in Table 5.3.8-3.
Table 5.3.8-3.
Recommended Plan Costs by Decade for the City of Dilley
|
Plan
Element |
2000 |
2010 |
2020 |
2030 |
2040 |
2050 |
|
Demand Reduction
(Conservation) (L-10 Mun) |
|
|
|
|
|
|
|
Annual Cost ($/yr) |
$12,504 |
$12,497 |
$12,523 |
$3,561 |
$3,550 |
$3,540 |
|
Unit Cost ($/acft) |
$245 |
$231 |
$220 |
$111 |
$108 |
$104 |
5.3.8.2 City of Pearsall
The City of Pearsall is projected to have adequate water supplies available from the Carrizo Aquifer to meet the city’s projected demand during the planning period.
Working within the planning criteria established by
the SCTRWPG and the TWDB,
it is recommended that the City of Pearsall implement the following water
supply plan
(Table 5.3.8-4).
§ Municipal demand reduction (conservation) to be implemented in 2000. This project can provide an additional 133 acft/yr beginning in year 2000, decreasing to 90 acft/yr of supply in 2050 (See Section 6, Supplement 2 and Volume III, Section 1.1).
Table 5.3.8-4.
Recommended Water Supply Plan for the City of Pearsall
|
|
2000
(acft/yr) |
2010
(acft/yr) |
2020
(acft/yr) |
2030 |
2040
|
2050 |
|
Projected Need (Shortage) |
0 |
0 |
0 |
0 |
0 |
0 |
|
Recommended Plan |
|
|
|
|
|
|
|
Demand Reduction (Conservation) (L-10 Mun) |
133 |
141 |
148 |
84 |
87 |
90 |
|
Total New Supply |
133 |
141 |
148 |
84 |
87 |
90 |
The costs of the recommended plan for the City of Pearsall are shown in Table 5.3.8-5.
Table 5.3.8-5.
Recommended Plan Costs by Decade for the City of Pearsall
|
Plan
Element |
2000 |
2010 |
2020 |
2030 |
2040 |
2050 |
|
Demand Reduction
(Conservation) (L-10 Mun) |
|
|
|
|
|
|
|
Annual Cost ($/yr) |
$32,648 |
$32,655 |
$32,629 |
$9,349 |
$9,360 |
$9,370 |
|
Unit Cost ($/acft) |
$245 |
$232 |
$220 |
$111 |
$108 |
$104 |
5.3.8.3 Rural Area Residential and Commercial
The rural area of Frio County is projected to have adequate water supplies available from the Carrizo Aquifer, Sparta Aquifer, and Queen City Aquifer to meet the water user group’s projected demand during the planning period.
5.3.8.4 Industrial
There is no projected industrial water demand in Frio County, therefore no water management strategies are recommended for this water user group.
5.3.8.5 Steam-Electric Power
Steam-electric power is projected to have adequate water supplies available from the Carrizo Aquifer, Sparta Aquifer, and Queen City Aquifer to meet the water user group’s projected demand during the planning period.
5.3.8.6 Mining
Mining is projected to have adequate water supplies available from the Carrizo Aquifer, Sparta Aquifer, and Queen City Aquifer to meet the water user group’s projected demand during the planning period.
5.3.8.7 Irrigation
Irrigation’s current water supply is obtained from the Carrizo Aquifer, Sparta Aquifer, Queen City Aquifer, and run-of-river rights. Irrigation is projected to need additional water supplies in the planning year 2000. The following options were considered to meet the irrigation projected need:
§ Demand Reduction (Conservation) (L-10 Irr.) (See Section 6, Supplement 2)
Working within the planning criteria established by the SCTRWPG and the TWDB, it has been found that it is not economically feasible to meet all of the projected irrigation needs at this time, since the cost of the water management strategies with enough water supply to meet the needs far exceeds the ability of irrigators to pay for the water. However, the irrigation water conservation option will meet a part of the projected irrigation needs in Frio County where further irrigation conservation opportunity exists. It is recommended that individual irrigators implement the following water supply plan to meet a portion of the projected need for irrigation (Table 5.3.8-6).
§ Demand Reduction (Conservation) to be implemented in 2000. This project can provide an additional 5,947 acft/yr of supply.
Table 5.3.8-6.
Recommended Water Supply Plan for Irrigation
|
|
2000
(acft/yr) |
2010
(acft/yr) |
2020
(acft/yr) |
2030
(acft/yr) |
2040
(acft/yr) |
2050
(acft/yr) |
|
Projected Need (Shortage) |
71,125 |
67,645 |
64,365 |
76,506 |
73,520 |
70,663 |
|
Recommended Plan |
|
|
|
|
|
|
|
Demand Reduction (Conservation) (L-10 Irr.) |
5,947 |
5,947 |
5,947 |
5,947 |
5,947 |
5,947 |
|
Total New Supply |
5,947 |
5,947 |
5,947 |
5,947 |
5,947 |
5,947 |
The costs of the recommended plan to meet the irrigation projected need are shown in Table 5.3.8-7.
Table 5.3.8-7.
Recommended Plan Costs by Decade for Irrigation
|
Plan
Element |
2000 |
|